Typical planning and installation process
The normal lead-in period for installation is 8 to 10 weeks. We will provide you with a dedicated Production Manager on call to assist you with your planning process, in advance of the installation.
A Step-by-Step guide to planning and installing your Signature Structure.
From receipt of order:
Week 1
- Book installation date with Fabric Architecture.
- Receive General Arrangement and Set-Out sheets for foundation pads.
- Obtain quotes for Fabric Architecture foundation package or contact a local contractor to excavate holes, pour foundations and make good the surface.
Week 2-3
- Confirm fabric and steel colours with Fabric Architecture.
- Fabrication of structure commences.
- Choose your preferred contractor and book date for ground works
(there must be at least 3 weeks cure time prior to installation)
Week 4
- Set-out, excavation and pouring of foundations to Fabrci Architecture's specifications.
- Fabric Architecture courtesy call to ensure foundations are completed.
Week 5-8
- Confirm site details with Fabric Architecture - dates, access, deliveries etc.
Week 8-10
- Fabric Architecture on site to complete installation
(regularly between 1 and 4 days depending on size of structure)
Week 11
- Chosen contractor returns to site to make good the surface.
Week 12
- Fabric Architecture sends completion certificate with Operations & Maintenance manual.